Homeowner guide

How Long Does an ADU Permit Take in Irvine, Anaheim, Santa Ana and Corona?

By Krishna Patel, Owner & Licensed General Contractor (CSLB #1132405) · Updated

The short answer

State law gives a city 15 business days to tell you whether your ADU application is complete, and 60 days to approve or deny a complete application when there is already a home on the lot. Inside that limit each city publishes something different: Irvine and Corona post plan review targets in working or business days, Anaheim's ADU Express is built to finish in days for eligible lots, and Santa Ana does not publish a review time for ADUs. The design work before you apply, and each round of plan check corrections, are what usually stretch the real timeline: in our experience, the whole ADU permit process typically takes 4 to 6 months.

The state deadlines every city has to meet

These are maximums for the city's review. They do not include the time to design the ADU, gather documents, respond to corrections, or pay fees, and they do not cover separate approvals such as an HOA review.

  • Completeness: the city must tell you in writing within 15 business days whether your ADU or JADU application is complete, and list what is missing if it is not. If it misses that deadline, the application is deemed complete.
  • Decision: once the application is complete, the city must approve or deny it within 60 days if there is an existing single-family or multifamily home on the lot.
  • Denials come with a full written list of what is deficient and how to fix it.
  • If you file the ADU together with a brand-new house, the city can hold the ADU decision until it acts on the house. You can also ask for a delay, which pauses the 60 days.

Irvine

  • Applications go in online through the IrvineReady! portal. After you submit, city staff check the package for completeness within approximately two business days, then email a link to pay fees.
  • Irvine does not publish an ADU-specific review time. Its plan review bulletin (No. 279) lists first-review targets that start once the Permit Counter processes the application, usually one to three working days after payment: 5 working days for residential remodels and additions, 20 working days for new residential construction, and 5 to 10 working days for later submittals.
  • The bulletin does not say which category a detached ADU or a garage conversion falls into, so ask the city which one applies to your project.
  • For new development and building expansions, plans are also routed to other reviewers (Planning, Public Works, Orange County Fire Authority and others), and no permit is issued until every section approves.

Anaheim

  • ADU Express: for eligible single-family lots using one of the city's free pre-approved detached plans, unmodified, the city says the review can be completed within 1 to 3 days, and that once you have paid the school fees, staff should be able to issue the approved building permit within one day.
  • Before that, Anaheim Public Utilities does a free "meter spot" visit, which the city says usually happens within three business days of your call, and the city's eligibility screening of your address and plan "can take a few weeks."
  • Custom ADUs, attached ADUs, conversions and JADUs go through the standard Building Division review. The city does not publish a review time for that path.

Santa Ana

  • Santa Ana does not publish a review time for ADU permits.
  • For its pre-approved ADU plans, which must be submitted through electronic plan check, the city asks you to allow up to 3 business days for staff to respond to your plan check request, and gives you 10 days to upload your files once invited.
  • Pre-approved plans qualify as Tier 2 projects with Planning and Building reviewing at the same time. After a pre-screen, the city sends two separate fee links (Planning and Building).

Corona

  • Corona reviews ADUs and JADUs ministerially through building plan check, and its municipal code says the city will act within 60 days of a completed application.
  • Its ADU process handout lists city review times for the building plan: 10 business days for the first review and 5 business days for each later review, plus 2 business days of processing, then 3 business days of plan approval processing for the permit.
  • Grading, fire sprinkler, landscape and solar plans are separate submittals with their own reviews, and the city notes that plans submitted at different times extend the review.
  • Corona is in Riverside County, so its rules differ from the Orange County cities around it.

What we see on real projects

The figures above are what each city officially publishes, and most of them cover a single step, such as a completeness check or one round of plan review. In our experience on Orange County area ADU jobs, the whole permit process typically takes 4 to 6 months.

That is our typical experience, not a city commitment. The timeline for your lot depends on the city, the design, how many rounds of corrections the plans need, and any other reviews the project triggers. We give you our best estimate for your address before you commit.

About Patel Precision Construction

We are a licensed Orange County general contractor (CSLB #1132405). We rebuild homes after water damage once a mitigation company has dried them out, working with your insurance adjuster, including Xactimate estimates and supplements. We also build ADUs and remodel kitchens and bathrooms. We do not do water extraction or drying.

ADU Construction in Orange County →

Common questions

Questions homeowners ask

How long does it take to get an ADU permit in Irvine?

Irvine does not publish an ADU-specific timeline. It checks a submitted ADU package for completeness in about two business days, and its plan review bulletin lists first-review targets of 5 working days for residential remodels and additions and 20 working days for new residential construction, starting after fees are paid and the application is processed. State law caps the decision at 60 days from a complete application when there is an existing home on the lot. In our experience, the whole ADU permit process typically takes 4 to 6 months.

Is there a fast-track ADU permit in Anaheim?

Yes. ADU Express is for eligible single-family lots using one of Anaheim's free pre-approved detached plans without changes. The city says the review can be completed in 1 to 3 days, though the eligibility screening before it can take a few weeks.

How long is ADU plan check in Corona?

Corona's ADU handout lists 10 business days for the first building plan review and 5 business days for later reviews, plus 2 business days of processing and 3 business days to process the approved plans for the permit.

Does Santa Ana publish an ADU permit timeline?

No. Santa Ana publishes the steps, not a review time. For pre-approved ADU plans it asks you to allow up to 3 business days for staff to respond to your electronic plan check request.